0As part of his role as a security manager, Denis provides the following chart to his organization's management team: a graph of time to remediate in days versus number of vulnerabilities. The curve begins at 50, gradually decreases, and reaches 0 between days 0 and 15. What type of measurement is he providing?
Answer Options
A
A coverage rate measure
B
A key performance indicator
C
A time to live metric
D
A business criticality indicator
Correct Answer: B
Explanation
Time to remediate a vulnerability is a commonly used key performance indicator (KPI) for security teams. Time to live relates to packet lifespans, business criticality measures importance of systems, and coverage rates apply to code testing.