The Domer Industries risk assessment team recently conducted a qualitative risk assessment and developed a matrix similar to the one shown here. Which quadrant contains the risks that require the most immediate attention?

Answer Options

A

I

B

II

C

III

D

IV

Correct Answer: A

Explanation

The risk assessment team should pay the most immediate attention to those risks that appear in quadrant I. These are the risks with a high probability of occurring and a high impact on the organization if they do occur.