hard
Single Answer
0Which one of the following actions is not normally part of the project scope and planning phase of business continuity planning?
Answer Options
A
Structured analysis of the organization
B
Review of the legal and regulatory landscape
C
Creation of a BCP team
D
Documentation of the plan
Correct Answer: D
Explanation
The project scope and planning phase includes four actions: a structured analysis of the organization, the creation of a BCP team, an assessment of available resources, and an analysis of the legal and regulatory landscape. Documentation of the plan occurs in later phases.