hard
Single Answer
0

Which one of the following actions is not normally part of the project scope and planning phase of business continuity planning?

Answer Options

A

Structured analysis of the organization

B

Review of the legal and regulatory landscape

C

Creation of a BCP team

D

Documentation of the plan

Correct Answer: D

Explanation

The project scope and planning phase includes four actions: a structured analysis of the organization, the creation of a BCP team, an assessment of available resources, and an analysis of the legal and regulatory landscape. Documentation of the plan occurs in later phases.