medium
Single Answer
0Which one of the following stakeholders is not typically included on a business continuity planning team?
Answer Options
A
Core business function leaders
B
Information technology staff
C
CEO
D
Support departments
Correct Answer: C
Explanation
While senior management should be represented on the BCP team, it would be highly unusual for the CEO to fill this role personally.