0Amanda is concerned about issues with dependencies that may be found during her pending change. What practice should she implement to help ensure unexpected dependency issues are not encountered?
Answer Options
A
Update organizational policies and procedures before the change.
B
Update functional diagrams before the change.
C
Validate the change in a test environment.
D
Document legacy applications that may create dependencies.
Correct Answer: C
Explanation
The most effective way to ensure that all dependencies have been satisfied is to perform the change in a matching test environment to ensure that all issues have been identified and resolved.