Amanda’s organization wants to conduct a risk assessment and needs to prioritize a timely completion of the process over rigorous detail. What type of assessment should she advise her organization to select?

Answer Options

A

Internal

B

External

C

Qualitative

D

Quantitative

Correct Answer: C

Explanation

Qualitative risk assessment uses knowledge and expertise to assess risk and are thus typically faster and more likely to be completed than a quantitative risk assessment. Quantitative risk assessments assign numeric values and calculations to determine relative risk. Choosing internal or external risk assessments is not a primary driver of speed compared to choosing quantitative over qualitative risk assessments.