medium
Single Answer
0Jackie's change management process involves reporting functional validation test results to stakeholders. Which of the following is not a common stakeholder or stakeholder group for an application upgrade?
Answer Options
A
Application administrators
B
Service owners
C
System administrators
D
Auditors
Correct Answer: D
Explanation
While auditors may request application version information during audits, they are not typically notified during normal application updates and patching cycles. Application administrators, service owners, and system administrators are all commonly notified about functional validation test results so that they can take further action or know that the service update is complete.