medium
Single Answer
0Mateo wants to conduct a fail over test for his datacenter. What will he need to do to accomplish this?
Answer Options
A
Turn off all systems in his datacenter.
B
Simulate what would occur during a datacenter outage.
C
Force a fail over using his network or other systems.
D
Cause an outage of a critical system.
Correct Answer: C
Explanation
Datacenters should have a fail over process that can be manually executed in case of emergency. Mateo should use that process to fail over to his organization's fail over site. Turning off every system in a datacenter is not recommended as this may lead to other unexpected failures. Simulation is not a fail over test, and creating an outage of a critical system typically will not cause an entire datacenter to fail over.