0The major patch release that Susan's team installed has failed, resulting in a nonworking service. What should her team do according to change management best practices?
Answer Options
A
Declare an outage.
B
Follow the documented backout plan.
C
Restore from backups to the previous version.
D
Uninstall the patch and validate service function.
Correct Answer: B
Explanation
Creating a complete backout plan and implementing it if something goes wrong that cannot be remediated during a change window is the accepted best practice in this scenario.