Which of the following change management processes does not commonly directly involve stakeholders outside of the IT organization?

Answer Options

A

Impact analysis

B

Building the backout plan

C

The change approval process

D

Determining the maintenance window

Correct Answer: B

Explanation

Administrators and system owners typically build backout plans. Stakeholders are involved in impact analysis as they help technical staff understand what the impact of changes will be on business areas. They engage in the change approval process, and they help to determine the maintenance window to ensure that impact on the business is minimized.